Friday, September 10, 2010
The landscaper is scheduled to continue the topsoil placement/parkway grading and start sodding next week. The final hot-mix asphalt surface course is scheduled to be paved later this month. The Village has a separate contract with Insituform Technologies to reline the sanitary sewer system and the storm system and will be on Windsor starting Tuesday. Residents will receive a door hanger the night before regarding limited water usage the day of the lining.