Friday, September 24, 2010

Landscaping has been completed. The final hot-mix asphalt surface course is scheduled to be paved next week starting Tuesday (weather dependent). Tuesday morning, the existing asphalt surface will be coated with fresh oil and sand. The oil will help the top coat of asphalt bond to the existing layer. The layer of sand is to help prevent tracking the oil into your driveways. Please try to keep your driving to a minimum while the oil dries. If you must drive on the oil, please drive slowly to help prevent splattering onto your vehicle. All vehicles must be removed from the roadway between 7:00 A.M. and 5:00 P.M. Parking is available on Wagner, Central and Surrey during daytime work hours.

The Village has a separate contract with Insituform Technologies to reline the storm system.

Friday, September 17, 2010

Landscaping has been completed. The final hot-mix asphalt surface course is scheduled to be paved later this month.

The Village has a separate contract with Insituform Technologies to reline the sanitary sewer system which has been completed and the storm system will be relined also.

Friday, September 10, 2010

The landscaper is scheduled to continue the topsoil placement/parkway grading and start sodding next week. The final hot-mix asphalt surface course is scheduled to be paved later this month. The Village has a separate contract with Insituform Technologies to reline the sanitary sewer system and the storm system and will be on Windsor starting Tuesday. Residents will receive a door hanger the night before regarding limited water usage the day of the lining.

Thursday, September 2, 2010

The structures in the road are being adjusted right now. The landscaper will be in within the next couple weeks, once they are finished grading along Indian Road.